Here are some photos showing what's happening on the the Anson Field.

6 Feb 2019: Preparing the site ready to install the electric supplies

6 Feb 2019: SSE installing the electric supplies to the site (trenches and conduit being pulled through) - and cutting through a resident's drive!

17 Feb 2019: Ground levelled and compacted for the office blocks to arrive

19 Feb 2019: Thomas Homes office and store cabins in place